At Banner Environmental Services, ensuring the safety of our clients and adherence to stringent environmental regulations is our foremost concern. Recently, we undertook a specialized asbestos-containing material (ACM) tile and mastic removal project at a residential property in Quincy, MA. This project not only demonstrated our technical expertise when it comes to small demolition and asbestos abatement but it also highlighted our commitment to maintaining the highest standards of safety and compliance.
Tile & Mastic Removal Project Scope and Location in Quincy, MA
The project in Quincy, Massachusetts, involved the removal of approximately 400 square feet of ACM tile and mastic from the basement and an additional 16 square feet from the rear hall adjacent to the kitchen. The scope also extended to the removal of a small staircase and the potential demolition of walls exhibiting tile and mastic beneath them.
Detailed and Professional Process When Working with ACMs
Our approach to ACM tile and mastic removal is both meticulous and comprehensive. Here is a step-by-step look into how we managed the Quincy project:
Initial Assessment and Planning
Before initiating any work, we conducted an in-depth assessment of the property, including a thorough inspection to identify all areas containing asbestos. Understanding the extent of asbestos contamination allowed us to develop a detailed plan tailored to the project’s unique needs.
Setting Up the Workspace for Asbestos Removal
The removal process mandated the establishment of a controlled environment to prevent asbestos fibers from being released into the living spaces. We achieved this by setting up a negative air HEPA-filtered workspace, coupled with a 3-stage decontamination unit. These precautions ensured the containment of airborne asbestos fibers, guaranteeing a safer environment for our team and the residents.
Physical Removal of Asbestos-containing Materials
The physical removal began with the enclosure of the affected areas using polyethylene sheeting, securely sealed with blue painter’s tape. This step is crucial to isolate the workspace and prevent cross-contamination.
Our trained technicians removed the ACM tile and mastic within this controlled environment. Our primary focus was the basement and the rear hall off the kitchen. Each tile was carefully detached, and the mastic beneath was scraped off with precision to avoid the release of asbestos fibers.
Safety Measures and Compliance
Our commitment to safety and compliance with environmental regulations is unwavering. For this project, our procedural adherence involved several key measures:
Asbestos Abement Regulatory Compliance in Massachusetts
Before commencing the project, we submitted a detailed notification form to the Massachusetts Department of Environmental Protection (DEP) as part of our compliance with local, state, and federal guidelines. This proactive measure signifies our dedication to handling hazardous materials responsibly.
Containment and Decontamination
The workspace was equipped with negative air machines fitted with HEPA filters, which significantly minimized the risk of airborne asbestos exposure. Additionally, a 3-stage decontamination unit was installed to ensure that all personnel and equipment exiting the workspace were thoroughly decontaminated, further preventing any possibility of asbestos fiber transmission.
Asbestos Waste Management
After the ACM tile and mastic were successfully removed from the property in Quincy, MA, all waste materials were meticulously packaged, labeled, and manifested. We transported the hazardous waste to an approved disposal facility, adhering to the strict disposal guidelines to mitigate environmental impact.
Independent Clearance and Project Completion
Ensuring the project’s complete and safe conclusion was paramount to us. To provide an additional layer of assurance, we coordinated with an independent hygienist for third-party air and visual clearance. This third-party verification confirmed that the environment was free from asbestos contamination, underscoring our comprehensive approach to safety and professionalism.
Asbestos Abatement in Quincy, MA: Project Impact and Commitment
The successful completion of the asbestos-containing material tile and mastic removal abatement project in Quincy, MA, is a testament to Banner Environmental’s diligence, expertise, and commitment to environmental safety. Our professional execution and unwavering adherence to compliance standards ensure that our projects meet and often exceed client expectations.
Need Help Removing Asbestos-Containing Materials from Your Property?
If you are a property owner in Quincy, MA, or any of the states we service in New England—Maine, Massachusetts, New Hampshire, Rhode Island, and Vermont—and have concerns about asbestos-containing materials, Banner Environmental Services is here to help. Our extensive experience and dedicated team provide top-tier services to ensure your safety and peace of mind. For more information, visit our Asbestos Abatement page. You can also learn more about our targeted Asbestos Abatement Removal methods and our Demolition services.
Contact us today to secure a safer environment for your home or business! With Banner Environmental Services, your safety is our priority.
24 HR Emergency Service: 866-934-2374